Friday, May 14, 2010


Quit embarrassed for not finishing this blog about the Walline Kitchen remodel. After my last entry of Nov 19, the wood floor got sanded down and stained and 1 coat of finish before Thanksgiving.
December 9, the Cambria Ashford color counter top got installed.
Dec 10-11 the carpenter, plumber and electrician came to set the appliances, hooked up the sink and dishwasher and generally finished the kitchen.
December 14 the wood floor was final coated
Dec 17-18 the tile backsplash was installed
A completed kitchen one week before Christmas (as CKC promised the Walline's)
As you can see by the pictures a beautiful Kitchen that makes the proud homeowners want to enjoy.

Wednesday, November 25, 2009

November 23-25
The existing oak wood floor is being sanded sealed and one coat of finish (final coat will be at end of job)


November 18, 2009

The cabinets were install enough to take a counter measure (see enclosed picture)

The home owner chose Cambria counters in Ashford color. The cabinet isntallation continued the balance of the week with the electrician coming Friday Nov 20, to install the puck lights inside and under the cabinet for task and accent lighting.

Monday, November 16, 2009

Nov 16, 2009
Cabinets were delivered this morning, they will be installed this week
Nov 11-12, 2009
Original Oak wood floor from the 1984 built home, was still in good condition, while the room was open (with out cabinets) the wood floor was sanded down to raw wood, ready to be refinished at a later date.
Nov 9-10, 2009
Home owner primed and painted the ceiling, walls and window casing

Tuesday, November 3, 2009

Nov 2-6 Sheetrock repair to walls and ceiling.